REMOVAL & INSTALLATION





Click image to see an enlarged view

Fig. Fig. 1 When removing nuts, bolts and other parts, place them in a tray or other container

  1. Raise car and place it on jackstands.
  2.  
  3. Drain the cooling system, transmission, and crankcase. Carefully lower the vehicle.
  4.  
  5. Scribe alignment marks on the underside of the hood and around the hood hinges, then remove the hood from the hinges.
  6.  
  7. Disconnect the coolant and heater hoses at the engine attachment.
  8.  
  9. Disconnect the battery cables from the battery.
  10.  
  11. Remove the radiator and shroud assembly. Remove the fan and pulley.
  12.  
  13. Remove the air cleaner.
  14.  
  15. Disconnect the coil, starter, and Delcotron wires, engine-to-body ground strap, oil pressure and engine temperature sender wires, and the CEC wire.
  16.  
  17. Disconnect the gas tank line from the fuel pump.
  18.  
  19. Disconnect the accelerator control linkage from the firewall.
  20.  
  21. Disconnect the hand choke linkage (four-cylinder) and the power brake vacuum line.
  22.  
  23. Disconnect the exhaust pipe from the manifold. On V8 engines, disconnect the crossover pipe.
  24.  
  25. Disconnect the clutch shaft bracket at the frame and disconnect the clutch linkage. On automatic transmission models, remove the transmission oil filler tube and plug the opening.
  26.  
  27. Attach an engine lifting tool. Attach it to a hoist and secure the engine.
  28.  
  29. Remove the driveshaft.
  30.  
  31. Remove the set aside the power steering pump and air conditioning compressor. Do not disconnect the hoses.
  32.  
  33. Remove the engine rear mounting bolts.
  34.  
  35. Disconnect the speedometer cable, transmission control rod linkage lower ends, TCS switch, and transmission oil cooler lines.
  36.