REMOVAL & INSTALLATION



See Figures 1 through 5



Click image to see an enlarged view

Fig. Fig. 1: Common starter motor mounting location



Click image to see an enlarged view

Fig. Fig. 2: Disengage the starter solenoid electrical connections



Click image to see an enlarged view

Fig. Fig. 3: Unfasten the starter retaining bolts



Click image to see an enlarged view

Fig. Fig. 4: Remove the starter retaining bolts



Click image to see an enlarged view

Fig. Fig. 5: Remove the starter from the vehicle

The following is a general procedure for all vans, and may vary slightly depending on model and series.

  1. Disconnect the battery ground cable at the battery.
  2.  
  3. Raise and support the vehicle.
  4.  
  5. Disconnect and tag all wires at the solenoid terminal.
  6.  

1975 and later starters do not require the R terminal. The High Energy Ignition System does not need a cable from solenoid to ignition coil.

  1. Reinstall all nuts as soon as they are removed, since the thread sizes are different.
  2.  
  3. Remove the front bracket from the starter and the two mounting bolts. On engines with a solenoid heat shield, remove the front bracket upper bolt and detach the bracket from the starter.
  4.  
  5. Remove the front bracket bolt or nut. Lower the starter front end first, and then remove the unit from the van.
  6.  
  7. Reverse the removal procedures to install the starter. Torque the two mounting bolts to 25-35 ft. lbs. (33-47 Nm).
  8.  

OVERHAUL



Brush Replacement
  1. Disconnect the field coil connectors from the starter motor solenoid terminal.
  2.  
  3. Remove the through-bolts.
  4.  
  5. Remove the end frame and the field frame from the drive housing.
  6.  
  7. Disassemble the brush assembly from the field frame by releasing the spring and removing the supporting pin. Pull the brushes and the brush holders out and disconnect the wiring.
  8.  
  9. Install the new brushes into the holders.
  10.  
  11. Assemble the brush holder using the spring and position the unit on the supporting pin.
  12.  
  13. Install the unit in the starter motor and attach the wiring.
  14.  
  15. Position the field frame over the armature.
  16.  
  17. Install the through-bolts.
  18.  
  19. Connect the field coil connectors to the solenoid.
  20.  

Starter Drive Replacement

  1. Remove the starter motor as previously outlined.
  2.  
  3. Disconnect the field coil connections from the solenoid terminal.
  4.  
  5. Remove the through-bolts.
  6.  
  7. Remove the commutator end frame, the field frame assembly and the armature assembly from the housing.
  8.  
  9. Remove the armature assembly from the housing. On some models it may be necessary to remove the solenoid and the shift lever assembly from the housing first.
  10.  
  11. Slide a small piece of 1 / 2 in. (12.7mm) pipe over the end of the shaft so the end of the pipe butts against the edge of the retainer. Carefully tap the end of the pipe with a hammer, driving the retainer towards the armature end of the snapring.
  12.  
  13. Remove the snapring from the groove.
  14.  
  15. Slide the retainer and clutch off the shaft.
  16.  
  17. To assemble the drive mechanism, slide the drive assembly onto the armature shaft after lubricating it with silicone.